A water tank is not something you buy every year. You put it in once, backfill around it or build next to it, and live with it. So the page you agree to matters more than most people realise. Many buyers compare one number against another, then discover that excavation was not included, that transport was extra, or that "waterproofed" meant nothing specific.
This checklist helps you read any quote like an owner who knows what to look for. It will not tell you who to choose. It tells you what to ask. Every question here is fair to put to any supplier, starting with us.
Know what you need first
You cannot judge a quote until you know your own requirement. Settle three things first.
- Capacity. People times 250 litres times days of reserve. A household of six uses 1,500 litres a day, so nine days of cover needs about 14 m³. Use the tank size calculator or the size guide.
- Space. The length, width and height you have available. That tells you whether a long or square footprint suits you.
- Installation type. Underground, or above ground on a base. Read how the two compare if you have not decided.
The whole checklist in one table
Hold any quote up against this table. If an answer is missing, that is a question to send before you say yes.
| Item | What the quote should say | Why it matters |
|---|---|---|
| Capacity | In m³ | Must match your usage sum |
| Dimensions | Length, width and height in metres | Confirms it fits your space |
| Type | Precast reinforced concrete, or other | Decides method and timing |
| Waterproofing | What goes inside, what goes outside | Protects water and concrete |
| Warranty | Length and what is covered | Tells you who deals with faults |
| Delivery and installation | Whether included, who provides the crane | Avoids surprise charges |
| Site preparation | Who digs, who builds the base | The biggest source of disputes |
| Openings and connections | What is ready and what is yours to arrange | Lets you prepare in advance |
| VAT | Shown as a separate line | Shows the true total |
| Date | A date, or how one is set | Lets you line up other trades |
Capacity and dimensions
Do not accept "a large tank" or "suitable capacity". You want a number in m³ and all three dimensions, since two tanks of equal capacity can take up quite different space.
Our own range shows why. The 22 m³ long tank is 3.70×2.70×3.30 m and the 22 m³ square tank is 3.30×3.30×3.00 m. Same capacity, about 10 m² of footprint against 10.9 m², and a 30 cm height difference. The 29 m³ long tank is just 2.50 m wide while the 29 m³ wide tank is 2.90 m. In a tight side passage, that difference decides the matter.
Dimensions are not the whole picture either. The pit or base has to be larger than the tank, so the crane can lower it and people can work around it. Our site preparation guide explains this.
Material and how it is made
Ask plainly whether the tank is cast in a factory or poured on your site. They are different methods, each with its own conditions, and reading precast versus cast in place will help you weigh the answer. Ours are precast reinforced concrete, cast and cured in our Al Suwaidi factory in Riyadh under engineering supervision, then delivered ready.
Comparing across materials is a different exercise altogether. Read concrete versus fiberglass and concrete versus plastic before you put numbers side by side.
Waterproofing what does it actually say?
"Waterproofed" alone is not enough. Ask what goes on the inside and what goes on the outside, and whether the inside material is suitable for stored water. If the tank will be buried, the outside matters as much as the inside, since moisture and groundwater press in from beyond the wall.
We use two layers a water-safe chemical lining inside and bitumen outside. Our guide to tank waterproofing explains why. Ask every supplier for the same clarity.
If your site is on the coast or has high groundwater, such as parts of Jubail and Jazan, raise it clearly before you agree, and share photos of the location.
Read the warranty line by line
People talk about warranties more than they read them. Ask
- How long does it run, and from when?
- Does it cover manufacturing only, or installation as well?
- Are cracks and leaks named explicitly?
- Who carries out the repair, and how do I report a fault?
- What is excluded, such as pumps or pipework done by others?
- Is it in writing?
Ours is 10 years on manufacturing and installation, covering cracks and leaks. Whoever you buy from, think about the parts someone else will install. A pump and the house pipework may be fitted by another tradesman, so settle who answers for what. You can read more on how we work to compare.
Delivery, crane and site work
This is where most surprises live. A concrete tank arrives by truck and is placed by crane. Be clear on who provides each, who pays for them, and whether "installation" means more than lowering the tank into place.
For us, delivery and installation are free inside Riyadh, and other cities have a fee based on size and distance. If you are in Jeddah, Madinah or Dammam, have the transport line written into the quote instead of estimating it yourself.
Ask these by name
- Who excavates for a buried tank?
- Who prepares the base?
- Who backfills after installation?
- What happens if the crane cannot reach on the day?
- How much space does the crane need?
You can also check truck and crane access yourself beforehand. Installation usually takes one day once the site is ready, so an unready site is what causes delays.
Openings and connections
Our tanks have inlet and outlet openings that connect to mains, a water truck, a well or a pump. The pipework around them is a separate matter. Ask any supplier about each item
- Is a float valve included?
- Are the overflow and vent provided for?
- Is a pump included?
- Who connects the tank to the house pipework?
- If two tanks are being linked, who does it?
Our plumbing connections guide and pump guide will help you make sense of the answers. If something is not included, that is fine. You just need to know, so your plumber is ready before installation day.
VAT and invoice
Check whether the figure includes VAT. Our written quote is free, shows VAT separately, and comes with an official tax invoice. This matters especially for contractors and companies that need the invoice for their accounts. Confirm whose name it will carry before you pay.
Also ask about payment stages and how long the quote stays valid. Written clarity saves trouble for both sides.
Comparing two quotes fairly
Do not compare only the bottom line. Make a simple table with one column per quote, and mark each item as included or not. Then work out what you would still pay for the missing items, such as digging, base, transport and backfill. A quote can look lower simply because it covers less.
Compare like with like same capacity, same installation type, same city. If one is precast and the other cast on site, timing and organisation differ too, and those count. Our concrete water tank guide covers the basics if you want more background.
Signs that call for a second question
- A verbal quote that never arrives in writing.
- Capacity with no dimensions.
- "Waterproofed" with no mention of which layer goes where.
- A warranty with no length or no scope.
- A figure with no mention of VAT.
- Vague answers about who digs and who backfills.
- Nobody asks to see your site, even in photos.
None of these automatically means trouble. Sometimes a supplier simply did not think to mention it. But asking costs nothing, and how they answer says a lot about how they will treat you after payment.
Projects and multiple tanks
Contractors and project owners should add the delivery schedule, site arrival order, tanks per load and how the tanks connect. We give special quotes for these cases and can install and connect several tanks. See the building water storage guide for residential work and our farm tanks page for agricultural projects.
Final check before you accept
- Capacity and dimensions are written and fit your space.
- Material and method of manufacture are clear.
- Waterproofing layers are named, inside and out.
- Warranty length and scope are written.
- Transport, crane and installation responsibilities are clear.
- Excavation, base and backfill are assigned.
- Connections are stated as included or yours to arrange.
- VAT is separate and the invoice is official.
- The date, or how it gets set, is written.
Ask for your quote