
Very few installation day problems have anything to do with the tank. The usual story is a pit a little too narrow, a floor that slopes, a car parked where the crane needs to stand, or a buried pipe the excavator found the hard way. Every one of those can be caught beforehand with a tape measure, a few photos and a phone call.
A precast concrete tank arrives finished from our Riyadh factory, so there is no formwork or concrete pour for the tank itself on your property. Your part of the job is the place it goes. Work through the stages below in order, because each one depends on the one before.
Stage 1 Settle the type of installation
Everything that follows depends on this. An underground tank needs a pit with a true floor. An above-ground tank needs a concrete base designed for the load. If you are still undecided, read our comparison of underground and above-ground tanks first.
Three questions usually make the decision for you. Can this ground be dug without unusual effort? Is groundwater likely to be close to the surface here? Do you need the yard space back after the work is finished? On coastal or salt-flat ground, read about tanks and high groundwater before anyone picks up a shovel, because the answer can change the plan entirely.
Then choose the exact spot. For homes, our article on where to put a tank in a villa works through the options one at a time.
Stage 2 Match the tank to the space
Work out how much water you need with the tank size calculator, then check what actually fits. The figures below are the tank's own dimensions, with nothing added for digging or pipework.
| Tank | Length × width (m) | Footprint | Height |
|---|---|---|---|
| 14 m³ | 3.55 × 2.30 | 8.2 m² | 2.80 m |
| 22 m³ long | 3.70 × 2.70 | 10.0 m² | 3.30 m |
| 22 m³ square | 3.30 × 3.30 | 10.9 m² | 3.00 m |
| 24 m³ | 4.40 × 2.90 | 12.8 m² | 2.90 m |
| 28 m³ | 4.35 × 3.35 | 14.6 m² | 2.90 m |
| 29 m³ long | 5.00 × 2.50 | 12.5 m² | 3.30 m |
| 29 m³ wide | 4.40 × 2.90 | 12.8 m² | 3.30 m |
Two things in that table are worth noticing before you dig. The 24 m³ and the 29 m³ wide share exactly the same footprint and differ only by 40 cm of height, so a pit cut for one can often take the other if the depth changes. And the two 22 m³ tanks hold the same water but behave very differently on site the long one is 60 cm narrower, while the square one is 30 cm lower.
Stage 3 Find out what is already in the ground
This is the step most often skipped and the most expensive to get wrong. Before any excavation, walk the site and answer these
- Where does the mains water pipe run between the meter and the house?
- Where do the electricity feeds go, including cables to boundary lights and gates?
- Where are the septic tank and the drain lines? The water tank should sit as far from them as the plot allows.
- Is there buried irrigation in the garden?
- Was anything dug and filled here before, such as an old tank or pit? Filled ground does not behave like undisturbed ground.
Dig out the building drawings if you have them, or ask whoever did the original plumbing. Then mark the routes on the ground with gypsum powder or string so the excavator operator can see them. A verbal description is not enough.
Also look at what is standing nearby. A deep cut close to a boundary wall or a house wall can disturb the soil supporting its foundation. If your spot is anywhere near a structure, ask an engineer to look before excavation starts and to decide on the set-back and how the sides will be supported.
Stage 4 Dig the pit for an underground tank
For an underground tank, give your contractor these points in writing rather than discussing them on the day.
Plan size. Tank dimensions plus enough room on every side for lowering, backfilling and pipe work. Tight pits are the most common cause of trouble on the day, and forcing a tank down risks scraping the bitumen layer on its outer face.
Depth. Tank height, plus any layer going under it, minus however far you want the top to stand above finished ground. Openings should not end up below ground level, where wash water, rain and dust can run in. Remember that finished level, after paving, may differ from the level you see today.
Sides. With tanks close to 3 m high, this is not a shallow trench. Loose and sandy soils can collapse without warning. The contractor decides on battering or shoring based on your ground, and nobody should climb down until the sides are safe.
Spoil. Do not heap it along the edge. The weight loads the sides of the pit, and the heap often ends up exactly where the truck or crane needs to be. Move what you will not reuse and put backfill material somewhere out of the way.
Safety. An open pit in a family home is a serious hazard. Put up a solid barrier from the first evening and keep it there until the tank is in.
Stage 5 Get the floor truly level
The tank has to bear evenly across its whole base. High spots and soft spots both concentrate load, and the load is large a full 24 m³ tank holds about 24 tonnes of water, on top of the weight of the concrete.
- Clear loose soil and any projecting stones.
- Compact the floor in the way your soil calls for until it is firm.
- Many contractors add a thin blinding layer of concrete over the compacted floor, which gives a clean, flat surface that is easy to check. Ask whether your site needs one.
- Check level in more than one direction with a proper instrument. Eyes are unreliable at the bottom of a deep pit.
- Measure both diagonals corner to corner. If they match, the pit is square and the tank will not bind on the way down.
Over-dug the floor? Do not throw loose soil back and hope. Uncompacted fill settles later under load. Bring the level back up in a way your contractor can stand behind.
If the tank sits above ground the base
There is no deep digging, but the base is real engineering and should not be improvised. It carries the concrete and the water all the time. A little arithmetic shows why one design cannot simply be copied from another site.
The 29 m³ long tank puts about 29 tonnes of water on 12.5 m², roughly 2.3 tonnes per square metre before you count the tank itself. The 14 m³ tank works out at about 1.7 tonnes per square metre. So
- Have an engineer design the base for your soil and your tank size.
- Build it larger than the tank by whatever margin that design calls for.
- Finish it flat. Any slope will show up in the water level inside.
- Avoid fresh fill underneath unless the engineer has specified how to treat it.
- Book the installation only when the engineer confirms the base can take the load.
- Plan drainage so water does not collect around its edge.
Ordinary yard paving is not a base. It was never built for this kind of load.
Stage 6 Bring the pipes to the right place
The tank has inlet and outlet openings that connect to mains, a water truck, a well or a pump. Running pipes is far easier before backfilling, so plan these routes now
- The fill line, from the mains or from where the truck will park. Trucks cannot stop just anywhere, so keep the fill point close to the street. Our water truck filling guide has the details.
- The suction line to the pump, with the pump itself somewhere ventilated and easy to service. See the tank pump guide.
- The overflow, and where it will drain. Never into the pit or onto the base.
- The vent, plus power for the pump and float switch.
Leave pipe ends ready but unconnected until the tank has settled into position. Ask us where the openings sit on your chosen size so your pipes arrive in the right spot, then follow our notes on tank plumbing connections.
Stage 7 Clear the way for the truck and crane
The street and the air above the site count as part of the site. Truck route, firm ground for the crane's outriggers, and a clear lifting path free of cables, trees and shades are all covered in our article on truck and crane access, along with the photos to send us.
One point belongs here specifically. If the crane will stand beside your pit, the edge of the pit has to be safe to stand near. Discuss the distance with us and your contractor beforehand rather than finding out on the day.
Timing the work around your date
The sequence is simple. Send your location and photos through our contact page or WhatsApp. You get a written quote with VAT shown separately, and a date. Then schedule the excavation or the base so that it is finished comfortably ahead of that date. Too early and the pit is exposed to rain, slumping and curious children. Too late and a truck and crane arrive at an unfinished hole.
The same order applies anywhere in the Kingdom. Delivery and installation are free inside Riyadh, and other cities have a fee based on size and distance, which appears in your quote. See the areas we serve.
How the ground changes the job
The stages are the same nationwide, but the ground is not. These are general patterns only, and your own site has the final word.
- Near the coast, in places like Jeddah, Dammam and Jazan, shallow groundwater and salty soil are more likely. Find out the water level before you fix the pit depth.
- In the mountains around Abha and Taif, rock near the surface and sloping plots are common, and above-ground can turn out simpler than excavating.
- On sandy plots and farmland, holding the pit sides and keeping the truck on firm ground become the main concerns. Our farm water storage guide goes further on this.
The day itself, and backfilling afterwards
The truck arrives, the crane places the tank, and we check that it is level and stable. With a ready site this usually takes one day. Keep someone on site who knows where the pipes and entrances are.
Backfilling is where people tend to rush. The outside of the tank carries a bitumen layer, so keep sharp stones away from it and bring the fill up evenly around all sides rather than from one direction. Our article on bitumen waterproofing explains why that layer matters.
After connection and the first fill, watch the joints and pipes. If the level drops without an obvious reason, go through our leak detection guide. The tank itself has a 10-year warranty on manufacturing and installation, covering cracks and leaks.
Final checklist
- Tank size settled and dimensions compared with the real space.
- Buried pipes and cables located and marked.
- Pit dug to the agreed size, or base confirmed ready for load.
- Floor level in both directions and diagonals equal.
- No standing water and no collapsed soil.
- Pipe ends ready and opening positions agreed.
- Spoil and materials clear of the truck and crane positions.
- Parked cars moved and neighbours told.
- Street and site photos sent and date confirmed.
Not sure about something? Photograph it and send it over rather than guessing. For the bigger picture, start with the complete concrete water tank guide or browse all tank sizes.
