In a villa, a day without water is an inconvenience that the family works around. In an apartment block, dozens of people depend on one reserve and every one of them expects you to fix it. So a building water tank is an operating decision as much as a construction one. This guide is for owners, compound managers and contractors who want to hand over a building and not hear about its water again.
For a single house or villa, use the water tank size guide instead. Here we focus on properties with more than one household.
Sizing water storage for an apartment building
The formula is the same, but it starts from the flats flats × people per flat × 250 litres × days. If you do not know the occupancy yet, start with 5 people for a family flat, then adjust for the kind of units you actually have.
- Large family flats may hold more than 5 people and use more per head.
- Studios and small units hold one or two people, but there are usually more of them.
- Furnished or serviced flats should be sized on full occupancy, because busy periods are when you get caught out.
- Staff housing has many rooms with several people in each, all using water at about the same times. Count beds, not rooms.
- Ground-floor shops on the same supply need their own line in the sum. A laundry or restaurant is nothing like a grocery or an office.
The size calculator works here too. Enter the total residents and try the 180, 250 and 350 litre rates to see the spread.
Storage by number of flats
This table uses 5 people per flat and 250 litres per person per day. The columns show how many days each tank group lasts when full.
| Flats | Residents | Daily use | One 29 m³ | Two (58 m³) | Three (87 m³) | Four (116 m³) |
|---|---|---|---|---|---|---|
| 4 | 20 | 5 m³ | 5.8 days | 11.6 days | 17.4 days | 23.2 days |
| 6 | 30 | 7.5 m³ | 3.9 days | 7.7 days | 11.6 days | 15.5 days |
| 8 | 40 | 10 m³ | 2.9 days | 5.8 days | 8.7 days | 11.6 days |
| 10 | 50 | 12.5 m³ | 2.3 days | 4.6 days | 7 days | 9.3 days |
| 12 | 60 | 15 m³ | 1.9 days | 3.9 days | 5.8 days | 7.7 days |
| 16 | 80 | 20 m³ | 1.5 days | 2.9 days | 4.4 days | 5.8 days |
| 20 | 100 | 25 m³ | 1.2 days | 2.3 days | 3.5 days | 4.6 days |
| 30 | 150 | 37.5 m³ | 0.8 days | 1.5 days | 2.3 days | 3.1 days |
You can also work backwards. Three days for 12 flats means 45 m³, so two 29 m³ tanks. Five days means 75 m³, so three. Numbers climb quickly with flat count, which is why a single tank rarely serves a large block on its own.
How many days should a building store?
A villa can happily hold a week of reserve. For a building, a full week may mean a very large volume that takes a long time to turn over. So rather than picking a number of days, ask which situation you need to cover.
- Mains with few cuts. Size for the longest cut you remember, plus a margin. An 8-flat building on one 29 m³ tank gets close to 3 days.
- Mains on a schedule. Cover the gap between supply turns, plus a day or two.
- Water trucks. Your storage has to take a full load when the truck arrives, and you need to know how many deliveries a week you really require. The water truck filling guide walks through this.
- Seasonal demand. In cities such as Makkah and Madinah, occupancy spikes in season. Size on the peak, not the average.
The case for two tanks instead of one
Even if a single tank could hold enough, a pair is often the better design.
- Cleaning without a shutdown. Isolate one, clean it, and residents never notice. See the tank cleaning guide.
- Repairs that do not stop the building. If one tank's pipework needs attention, the other carries on.
- Flexible siting. If you have no single spot for both, place them apart and connect them.
- Room to grow. Add a floor or change the unit mix and you add a tank rather than replacing one.
Valves make or break this. Each tank must isolate independently without stopping the other. Connect two tanks with no isolation valve and you lose most of the benefit. This gets planned before digging, not after. Tank plumbing and connections covers the inlet and outlet side.
Which size suits a building?
Buildings tend toward the larger tanks, since you want the most volume from the fewest units. The shape of the plot then picks the model.
| Size | Dimensions and height | Where it tends to fit |
|---|---|---|
| 29 m³ long | 5.00 × 2.50 m, 3.30 m high | Side setbacks and strips along a boundary wall |
| 29 m³ wide | 4.40 × 2.90 m, 3.30 m high | A rear yard, or a corner shorter than 5 m |
| 28 m³ | 4.35 × 3.35 m, 2.90 m high | Limited height with enough width to spare |
| 24 m³ | 4.40 × 2.90 m, 2.90 m high | Small blocks of four to six flats where height is limited |
Those dimensions show you how a row behaves. Two 29 m³ long tanks end to end take 10 metres by 2.50 metres, so a narrow strip down one side of the building can hold 58 m³. Side by side they make a 5 by 5 metre block before working gaps. Two 29 m³ wide tanks side by side come to 5.80 by 4.40 metres. Allow extra on top of all of these for access and work space.
Underground or above ground?
Land is usually tight and valuable on a building plot, so an underground tank tends to win the surface stays usable and the frontage stays clean. Above ground on a base saves the excavation and makes inspection easier, which suits projects with spare ground at the rear. See underground water tanks and our comparison of underground and above ground tanks for the detail.
Check the ground before you settle on it. On the coast in places like Jeddah, Dammam and Jubail, groundwater can sit close to the surface, which changes how excavation and installation are done. Read about tanks in high groundwater and mention it in your first message to us.
Getting water from the tank up to the flats
A ground tank will not lift water to the fifth floor by itself. There are three common arrangements.
- Pump to roof tanks. A pump fills tanks on the roof and water runs down to the flats by gravity. You keep a small reserve overhead if the power fails.
- Direct pressure from a booster set. No roof tanks and steady pressure, but a power cut stops the water unless you have a backup supply.
- A mix of both. Some floors on pumps and some on roof tanks, depending on the network design.
Whichever you use, keep a standby pump. A spare on site is far easier than a building full of phone calls when the duty pump fails. The project engineer or plumber sets pump capacity by the number of floors, and our tank pump guide tells you what to ask them.
Who pays for the water?
This is not a tank question, but it arrives as soon as the tank is connected. A shared tank means shared consumption, and owners usually handle it one of two ways.
- Sub-meters per flat. Each resident pays for what they use. It is fair, and people notice leaks faster. It does have to be planned along with the pipework.
- A fixed split between flats. Simple to run, but a small flat pays the same as a large one, and that breeds complaints.
In a new building, deciding now is far easier than altering the network later. Either way, put a meter on the filling line so you can compare what goes in with what comes out. That meter is usually the first thing to reveal a leak, and how to detect a tank leak takes it from there.
Compounds grouped tanks or one per building?
A compound gives you a bigger choice than a single block does.
| Question | Tanks grouped in one yard | A tank set for each building |
|---|---|---|
| Space | Needs one large yard | Spreads across building setbacks |
| Pipework | Long main network, central pumps | Shorter runs, pumps per building |
| Filling | Truck stops at one point | Truck moves between buildings |
| Faults | Can reach the whole compound unless zoned | Stay inside one building |
| Expansion | Add tanks if the yard has room | Each phase brings its own tanks |
Here is a worked example. Five buildings of 8 flats with 5 people per flat make 200 residents and 50 m³ a day. Three days of storage means 150 m³, so six 29 m³ tanks in a group, totalling 174 m³ and lasting about 3.5 days. Spread out, each building uses 10 m³ a day. Two 29 m³ tanks per building gives about 5.8 days, using ten tanks in all.
A villa compound works differently. Twenty villas with 6 people each come to 120 residents and 30 m³ a day. Each villa could have its own tank and run independently, as described in villa water tanks, with the 14 m³ size for tight plots. On a shared system, four 29 m³ tanks give 116 m³, or about 3.9 days.
As a broad pattern, per-building tanks serve spread-out sites because pipes stay short and faults stay contained. Grouped tanks suit compact compounds with a service yard. The project engineer makes the final call against the site plan.
For contractors fitting tanks into the programme
A precast concrete tank reduces site work because it is cast and cured in our factory and arrives ready. That only pays off if a few things are sorted early.
- Secure access before the structure rises. The truck and crane need a way in, and a finished building may remove it. See crane and delivery access.
- Have the pit or base ready by the date. Installation usually takes one day once the site is ready. The site preparation guide lists what that means.
- Fix opening positions with your plumber. Inlet and outlet connect to mains, water truck and pump.
- Raise any firefighting water requirement early. It comes from the project engineer and is calculated separately. Tell us at the start so the tank count reflects it.
- Get one written quote for the whole job. Multiple tanks get a special quote, with VAT shown separately and an official tax invoice.
If you are weighing this against pouring on site, read precast versus cast-in-place tanks.
Running the tanks after handover
Nobody in a building looks after the tank unless someone is told to. Name one responsible person, whether that is a caretaker, a management company or the owner, and give them a short list.
- Water level and meter readings, to catch unusual use early.
- The float valve and pump sound, because a pump that cycles for no reason is a warning sign.
- Access covers closed and protected. See keeping tank water clean.
- A cleaning schedule that tells residents in good time if there will be an interruption.
Each tank carries a 10-year warranty on manufacturing and installation, covering cracks and leaks. It has two waterproofing layers, a water-safe chemical lining inside and bitumen outside, so remember that outer layer when anyone digs or works around it. More in tank waterproofing and bitumen.
Adding storage to an existing building
Many older buildings were designed around fewer units or lighter use. If residents are complaining, find the actual cause first. Is the tank really too small, is a leak eating the reserve, or is the pump too slow to refill the roof tanks? Compare real consumption with the sums above.
If the old tank itself is the problem, read signs it is time to replace a water tank. Often the answer is adding a new concrete tank in a setback or rear yard and tying it into the existing network. Access is the deciding factor on built-up sites, so photograph the street, the gate and the space first.
What to send us for a quote
Send the project location, the number of flats and buildings, and photos of the site and street on WhatsApp. Tell us whether the structure is standing or still being built, and whether you want tanks underground or above ground. We reply with a written quote and a date.
Our factory is in Riyadh, where delivery and installation are free. We also serve every other region of the Kingdom for a fee based on size and distance. You can read why owners choose Concrete Tank, and the FAQ answers most other questions.